June 17th

Scafolding is up to work on the outside of the building, the front is covered, the masonry walls are almost complete and look we have sidewalks!

June 10th

Painting the inside, a look at the outside, and the roof being put on the front of the complex.

June 5th

Dry wall being out up, and the lights are working!

May 29th

Lights, air ducts, and more work on the front.

May 22nd

Rafters for the front of the building and metal studs for dry wall to hide the coolers.

May 20th

Work on the front of the building and the parking lot.