Starting on the front

Now that the concrete for the sports portion of the building is done, they have started to work on the office, classroom, and pro shop portion of the building.


With the walls complete and the footings on the front portion of the building poured our cement truck total is now 175!

Applying the Steel

First the steel to support the walls was put into place...


Then came the steel for the roof...

Now when you walk onto the site it feels like you are walking into a building.