Scafolding is up to work on the outside of the building, the front is covered, the masonry walls are almost complete and look we have sidewalks!
Week of April 30th
The precast concrete installed, one end of the building is being closed, and the front of the building is coming along.
The Roof
The roof is up. Once they started it did not take long. It is amazing how much cooler it is with just the shade of the roof. Come summer time it is going to be a great place to play! Now it is just a question of when.
Block Walls
This is the block wall for the front portion of the building where the shop, offices and classrooms will be.
Adding some Color
It may only be white paint and green facia, but now the Sports Complex has some color along with that some character.
Starting on the front
Now that the concrete for the sports portion of the building is done, they have started to work on the office, classroom, and pro shop portion of the building.
With the walls complete and the footings on the front portion of the building poured our cement truck total is now 175!
Applying the Steel
First the steel to support the walls was put into place...
Then came the steel for the roof...
Now when you walk onto the site it feels like you are walking into a building.
Lifting the Walls
After a long wait, the walls are up. They started @ 7:30am on Mon. 1/14 and finished at about 2:30pm. It took 7 hours to lift up 42 walls. It was amazing to watch!
Pouring the Walls
They are done! The walls have been poured and are curing. They will sit for a week and then hopefully be raised starting the 10th.