June 17th

Scafolding is up to work on the outside of the building, the front is covered, the masonry walls are almost complete and look we have sidewalks!

June 10th

Painting the inside, a look at the outside, and the roof being put on the front of the complex.

June 5th

Dry wall being out up, and the lights are working!

May 29th

Lights, air ducts, and more work on the front.

May 22nd

Rafters for the front of the building and metal studs for dry wall to hide the coolers.

May 20th

Work on the front of the building and the parking lot.

The Coolers

These coolers are huge and a semi-truck can turn around inside of the complex.

May 6th

More pictures of the outside. The mezanean down the center of the compex and over the snack bar.

May 1st

A look at the outside of the BFSC.

Week of April 30th

The precast concrete installed, one end of the building is being closed, and the front of the building is coming along.

Week of April 22nd

The precast concrete is being put into place for the coolers and the parking lot lights are put in.

View from a distance

Progress of the BFSC.

The Inside

The ceiling on the inside, and locker rooms.

The Roof

The roof is up. Once they started it did not take long. It is amazing how much cooler it is with just the shade of the roof. Come summer time it is going to be a great place to play! Now it is just a question of when.

Block Walls

This is the block wall for the front portion of the building where the shop, offices and classrooms will be.

Adding some Color

It may only be white paint and green facia, but now the Sports Complex has some color along with that some character.

Starting on the front

Now that the concrete for the sports portion of the building is done, they have started to work on the office, classroom, and pro shop portion of the building.


With the walls complete and the footings on the front portion of the building poured our cement truck total is now 175!

Applying the Steel

First the steel to support the walls was put into place...


Then came the steel for the roof...

Now when you walk onto the site it feels like you are walking into a building.

Lifting the Walls

After a long wait, the walls are up. They started @ 7:30am on Mon. 1/14 and finished at about 2:30pm. It took 7 hours to lift up 42 walls. It was amazing to watch!

Pouring the Walls

They are done! The walls have been poured and are curing. They will sit for a week and then hopefully be raised starting the 10th.